Telangana CM Revanth Reddy conducted a review on Hyderabad Metro Railway. The CM discussed with the officials about the extension of the metro line and the current situation. Officials gave a power point presentation to the Chief Minister on the plans for Metro route to Shamshabad Airport. CM Revanth Reddy, who has already given clarity that the metro to the airport will not be canceled, said that they are streamlining them keeping in mind several factors. CM Revanth said that the distance from BHEL to the airport will be 32 km. There will be a metro from MGBS to Shamshabad Airport via Patabasti. It has been revealed that a metro line will be linked from Nagol to the airport at Chandrayanagutta via LB Nagar and OyC Hospital.
Revanth Reddy clarified that if necessary, the metro from Miyapur to Ramachandrapuram and Mind Space will be extended to the financial district. They told media persons on New Year’s Day that the metro lines they are proposing will be less than the amount proposed by the previous government. Accordingly, CM Revanth Reddy, who conducted a review with the officials, advised the officials to work on expansion of Metro and new routes.
Items reviewed..
The government is planning to develop Hyderabad Metro in five sectors. To this extent, the CM ordered to give an early report on the study on Metro Phase-2.
* Proposals should be prepared for laying 100 feet road from Darushifa Junction to Salibanda and from Darushifa to Falaknuma.
* For road winding, a meeting should be held with the local public representatives and suggestions and objections should be taken.
* Due care should be taken and coordinated as there are 103 religious houses of worship and heritage buildings on this route.
* Miyapur-Chandanagar-BHEL-Patan Pond (14 km).
* MGBS-Falaknuma-Chandrayanagutta-Mylardevpally-P7 Road-Airport (23 km).
* Nagol -LBnagar-Owaisi Hospital – Chandrayanagutta – Mailardevpally – Aramgarh – New High Court site at NH Rajendranagar (next to Agricultural University Main Gate) (19 KM)
* Extension of Corridor-III from Raidurg Station to Financial District (Wipro Lake Jn/American Consulate) via Biodiversity Jn, IIIT Jn and ISB Road (12 km).
* LBnagar-Vamsthalipuram-Hayatnagar (8 km).
* Plan for Metro rail connectivity from airport area to Kandukur on Srisailam highway.
* Metro Phase-III plans to extend from JBS Metro Station to Shamirpet.
* Plan to extend Metro from Paradise Metro Station to Kandlakoya/Medchal – CM.
* Metro Rail Plans on Musi Riverfront East-West Corridor from Taramatipet to Nagole, MGBS (40 km) to Narsinghi.
* CM Revanth Reddy suggested that these plans should be prepared quickly in a comprehensive manner and written to Union Minister Hardeep Singh Puri.